North Loop Reconstruction & Pedestrian Improvements Update
Editor's note - This is an ongoing series of updates as the North Loop Reconstruction and Pedestrian Improvements project.
North Loop Reconstruction & Pedestrian Improvements
The North Loop Reconstruction & Pedestrian Improvements Project consists of two separate projects:
- A full street reconstruction along 3rd St N between 10th Ave N and 5th Ave N
- A pedestrian improvement project generally bounded by 10th Ave N on the north, 1st Ave on the south, West River Parkway on the east, and 4th St N on the west
What's Happening
.
5th Ave N
- CenterPoint Energy made it though the intersection of Washington and 5th Ave N and is currently at 3rd St N working towards 4th St N
- Started sidewalk removals on the east side of 5th, the west side will remain available for pedestrian access
- Removed old railroad tracks
7th Ave N
- Pavement has been removed
- Removed old railroad tracks
- Utility work has begun between 3rd St N and 4th St N (above photo 13' deep sanitary sewer manhole rebuild)
- The soil conditions are very poor in the area, this will be remedied as soon as
For more information on this project, visit the project website.
Upcoming Work
.
WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK
5th Ave N
- CenterPoint Energy 6” gas line installation continuing from 3rd St N to 4th St N
- Finish sidewalk removals on the east side of 5th Ave N
7th Ave N
- Continue utility work
- Water system upgrades – There is a water shut-off planned along 7th Ave N on Tuesday night beginning at 11 pm and ending around 5 am Wednesday morning. If your property is effected, a blue notice will be placed on the door of your property in 48 hours’ in advance for impacted businesses, 24 hours’ in advance to impacted residential properties.
- Sanitary Sewer – Crews are currently reconstruction sanitary structures on 7th Ave N
- Storm Sewer - Storm sewer work will begin tomorrow
8th Ave N – Tentatively planning on right after Memorial Day
- Begin salvaging brick pavers on 5-29-19
- Followed by full depth removals
9th Ave N
- Begin salvaging brick pavers on 5-31-19
.
Updates
.
Project still scheduled to begin June 17, 2019.
For more information on this project, visit the project website.