Kim Eslinger
Editor
612-321-8040
kim@millcitymedia.org

Brianna Ojard
Associate Editor

David Tinjum
Publisher
612-321-8020
dave@millcitymedia.org

Claudia Kittock
Columnist / Non-Profits
Email Claudia...

Becky Fillinger
Small Business Reporter
Producer / Milling About
Email Becky...

Michael Rainville Jr.
History Columnist
Email Michael...

Doug Verdier
River Matters

Mill City Times is a not-for-profit community service. We do not sell advertising on this site.

Community Partners

Thanks to our community partners, whose support makes Mill City Times possible:

MILL CITY FARMERS MARKET

With over 100 local farmers, food makers and artists, MCFM strives to build a local, sustainable and organic food economy in a vibrant, educational marketplace.

Visit their website...

HENNEPIN HISTORY MUSEUM

Hennepin History Museum is your history, your museum. We preserve and share the diverse stories of Hennepin County, MN. Come visit!

Visit their website...

MEET MINNEAPOLIS

Maximizing the visitor experience of Minneapolis for the economic benefit of our community, making Minneapolis the destination of choice among travelers.

Visit their website...

MSP FILM SOCIETY

Promoting the art of film as a medium that fosters cross-cultural understanding, education, entertainment, and exploration.

Visit their website...

GREAT RIVER COALITION

Enhancing the Minneapolis riverfront environment—for people and pollinators.

Visit their website...

Cultural Cornerstones
Search Mill City
Recent News
Front Page Archives
Friday
Jul122019

North Loop Reconstruction & Pedestrian Improvements

Editor's note - This is an ongoing series of updates as the North Loop Reconstruction and Pedestrian Improvements project.

North Loop Reconstruction & Pedestrian Improvements

The North Loop Reconstruction & Pedestrian Improvements Project consists of two separate projects:

  1. A full street reconstruction along 3rd St N between 10th Ave N and 5th Ave N
  2. A pedestrian improvement project generally bounded by 10th Ave N on the north, 1st Ave on the south, West River Parkway on the east, and 4th St N on the west

North Loop Reconstruction Updates

WORK THIS PAST WEEK

5th Ave N

  • Continuing water work at 5th and 3th St N

7th Ave N

  • Grading complete
  • Gas work complete

8th Ave N

  • Finished removing poor soils and backfilling
  • Finished placing aggregate base, in preparation for paving the first lift of asphalt

9th Ave N

  • Finished utility work
  • Finished removing poor soils and backfilling
  • Began placing aggregate base in preparation for paving the first lift of asphalt

3rd St N

  • Continued water work between 8th Ave N and 5th Ave N

WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK

5th Ave N

  • Continuing water work at 5th and 3rd St N (8th Ave N to 5th Ave N), there will be a temporary water shut off on the night on Sunday July 14, 2019. If your property is effected, a notice will be placed on the door of your property  48 hours’ in advance for impacted businesses, 24 hours’ in advance to impacted residences
  • Starting the removal of poor soils -work will begin at 4th St N and move towards Washington, this work may impact traffic flow on 5th Ave N
  • Starting storm sewer work

7th Ave N

  • Tentatively planning on placing the first lift of asphalt 7-17 and 7-18
  • If the first lift of asphalt is placed on 7-17/7-18, curb and gutter installation will follow

8th Ave N

  • Tentatively planning on paving 7-17 and 7-18 at Washington and 8th Ave N (not the entire stretch, just the Washington end)
  • If the first lift of asphalt is placed on 7-17/7-18, curb and gutter installation will follow at the intersection of Washington and 8th Ave N
  • If the first lift of asphalt is placed on 7-17/7-18, curb and gutter installation will follow at the intersection of Washington and 8th Ave N
  • Access to properties between Washington and 3rd St N will partially reopen at Washington.

9th Ave N

  • Finish placing aggregate base in preparation to place the first lift of asphalt at Washington and 9th Ave N
  • Tentatively planning on paving 7-17 and 7-18 at Washington and 9th Ave N (not the entire stretch, just the Washington end)
  • If the first lift of asphalt is placed on 7-17/7-18, curb and gutter installation will follow at the intersection of Washington and 9th Ave N
  • Access to properties between Washington and 3rd St N will partially reopen at Washington.

3rd St N

  • Isolated removals for water work only between 8th Ave N and 5th Ave N, there will be a temporary water shut off on the night on Sunday July 14, 2019. If your property is effected, a notice will be placed on the door of your property in 48 hours’ in advance for impacted businesses, 24 hours’ in advance to impacted residences
  • Begin salvaging brick pavers, crews will start on the north ½ of 3rd St, all meters along 3rd St N are hooded between 5th Ave N and 10th Ave N in order to maintain two way traffic on 3rd St N

For more information on this project, visit the project website.

North Loop Pedestrian Improvements Updates

WORK THIS PAST WEEK

2nd St N NW Corner

  • Crews were off the job from June 27 through July 8
  • Started saw cutting on 1st St N at 2nd, 4th and 5th Aves N

WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK

2nd St N NW Corner

  • 4th Ave N pour remaining concrete
  • 5th Ave N pour remaining concrete
  • 8th Ave N begin installing conduit for new pedestrian flasher system

1st St N

  • 1st St N and 3rd Ave- Water work, 9 meters will be hooded between 2nd Ave N and 3rd Ave N to maintain two way traffic during the work.  The water work is expected to take less than two weeks. there will be a temporary water shut off on the night on Wednesday, July 17, 2019. If your property is effected, a notice will be placed on the door of your property in 48 hours’ in advance for impacted businesses, 24 hours’ in advance to impacted residences
  • 3rd Ave N – NE corner will be removed
  • 2nd Ave N -SW corner will be removed
  • 1st Ave N – SW corner will be removed

4th Ave and W River Parkway

  • SE corner will be removed
  • Replacement work may begin

For more information on this project, visit the project website.

Miscellanious

Stakeholder Meeting -These meetings are informal, held biweekly and intended to offer residents and businesses on the job an opportunity to get construction updates, ask construction and access related questions.

Date/Time: July 24, 7:30 am to 8:30 am

Location:  Corner Coffee 514 N 3rd St #102, Minneapolis MN 55401

As always, feel free to contact myself (612-673-3365) or John Benjamin (651-443-1096) with any construction related questions or concerns.

Contact Information

Project Manager:

Stephanie Malmberg, stephanie.malmberg@minneapolismn.gov, 612-673-3365

Chief Field Inspector:

John Benjamin, john.benjamin@minneapolismn.gov, 651-443-1096

« Get Ready for the 2019 Aquatennial - July 24 thru 27! | Main | Arts, Culture and the Creative Economy Program Newsletter »