North Loop Paving and Pedestrian Improvement Project Updates
North Loop Reconstruction & Pedestrian Improvements
The North Loop Reconstruction & Pedestrian Improvements Project consists of two separate projects:
- A full street reconstruction along 3rd St N between 10th Ave N and 5th Ave N
- A pedestrian improvement project generally bounded by 10th Ave N on the north, 1st Ave on the south, West River Parkway on the east, and 4th St N on the west
North Loop Reconstruction Updates
- Lighting installation is almost complete, it is anticipated that the luminaries will all be installed within the next three weeks
- Sod installation will begin in May
- Tree planting is tentatively scheduled to begin in late April
For more information on this project, visit the project website.
North Loop Pedestrian Improvements Updates
- This project will start back up on April 6, 2020
- Initial work will begin on the south side 2nd Ave N/2nd St N
- The work on 2nd Ave N/2nd St N is anticipated to take three weeks
- Buses will be rerouted while this work is occurring (see Metro Transit web site for detail)
- On the week of April 13, the SW corner of 1st AveN/2nd St N will completed
- Remaining work on 8th Ave N/2nd St N and 10th Ave N/2nd St N will also be completed mid to late April
For more information on this project, visit the project website.
Contact Information
Project Manager:
Stephanie Malmberg, stephanie.malmberg@minneapolismn.gov, 612-673-3365
Chief Field Inspector:
John Benjamin, john.benjamin@minneapolismn.gov, 651-443-1096