May 7th Bridge 9 Improvement Project Update


Bridge No. 9 was constructed in 1922 by the Northern Pacific Railroad to carry freight over the Mississippi. The City of Minneapolis acquired this bridge in 1986 and converted the bridge to a pedestrian use bridge in 1999. The bridge currently provides a Mississippi River crossing for the Dinkytown Greenway bike trail.
Beginning in April, 2025, the City of Minneapolis started making repairs and improvements to Bridge 9, Abutment 1 and the approach spans on both ends of the bridge
* * * Latest project news * * *
2025 Construction Phase
Public Works has been working on this bridge in phases over the past few years, starting with the substructure work (piers and abutments).
In 2025, the scope of work will focus on the superstructure, which includes removing and replacing the approach span decks, replacing the existing railing with a high-safety railing and rehabilitating the east side abutment.
Rehabilitation work on the abutment consists of the removal of degraded concrete, then repairing and strengthening the concrete to remain with new reinforced concrete. The work on the approach spans consists of the removal of the old ballast slab/deck, aggregate and bituminous pavement, then constructing a new reinforced concrete deck.
View of removed bridge deck
The abutment work takes place within Bridge 9 right of way through University of Minnesota property. It is occurring adjacent to the U of M Main Energy Plant. Access and staging for the work were closely coordinated with University officials.
Sawing concrete slab
Schedule
Construction activities this season started on April 7th of 2025. The scheduled completion date is the end of December 2025. The contractor is currently anticipating substantial completion by the end of November 2025.
Traffic Impact
The bridge is closed to bicyclists and pedestrians this season. The Detour route is below, and it is also posted to the project webpage.
Current Work
For the month of April, the following construction operations were performed: Work site establishment, installing the debris containment system, removal of the aggregate and bituminous surface on the approach spans, saw cutting the northern approach span for deck removal and beginning to remove the deck on the northern approach span.
Removal of concrete slab section
Coming Up
Continued deck removals, railing removals, excavation on the North side of the bridge to allow for work on Abutment 1.
Stay Connected
For more details and to sign up for email updates please visit the project page.
For concerns or questions about the Bridge 9 project please contact:
Contact the project engineer: Petru Vizoli,
612-201-1905, or Petru.Vizoli@minneapolismn.gov
Contact the engineer: Oscar Weber,
651-470-4790 or Oscar.Weber@minneapolismn.gov
Contact the design team project manager: Rich Revering,
612-718-8412 or Richard.Revering@Bolton-Menk.com