James I. Rice Parkway Resurfacing Begins Next Week
Via an August 5 e-newsletter from the Minneapolis Park & Recreation Board:
Pavement resurfacing work is scheduled to begin on James I. Rice Parkway between Plymouth Avenue and Hennepin Avenue on August 12.
The parkway will be closed between Plymouth Avenue and Portland Avenue for a total of about five days while crews remove and replace a portion of the parkway asphalt surface. The parkway will reopen over the weekend beginning Friday evening, August 14, and close again Monday, August 17 to finish the paving.
In preparation of the pavement resurfacing, small segments of the concrete curb and gutter located along the edge of the parkway will be removed and replaced starting August 6. This work will be completed without closing the parkway to vehicle traffic.