Hennepin Avenue Downtown Reconstruction Project Update
Utility work continues on the corridor. The major scopes of work are Xcel Energy duct bank and manhole replacement, and City Sanitary Sewer Replacement.
What's Coming Up
The Sanitary Sewer replacement work is nearing the end of their Phase 1 work within the 12th Street Intersection. The Intersection will remained closed until Monday. Following that work the pavement restoration will continue until mid next week.
Xcel Energy is progressing on the both ends of the corridor with both underground construction and new electrical cable pulling operations. This work will continue through the winter months.
For more detailed information please see attached update.
For more information on this project contact: