Hennepin Avenue Downtown Reconstruction Project Update
Underground Utility work continues on the project. The sanitary sewer work has progressed across 11th St. and will continue south toward 12th St. Xcel Energy has completed their manhole and duct bank construction from Washington to 4th on the north end of the project. Xcel Energy has also completed some of the manhole work south of 7th.
What's Coming Up
The sanitary sewer work will continue their work south of 10th St.
Xcel Energy will begin their cable pulling work between Washington and 4th St. They will also continue the manhole and duct bank construction south of 4th st. Xcel will begin moving south of 8th St. with the other crews as well.
See update attached for more details
For more information on this project contact: