Hennepin Avenue Downtown Reconstruction Project - June 9 Update
Hennepin Avenue Downtown Reconstruction Project
Hennepin Ave. will be reconstructed between 12th Street and Washington Avenue. The City will reconstruct the pavement from building face to building face, including improvements to public and private utility infrastructure, and improved space for pedestrians, bicycles, transit, and vehicles.
Latest Project News
The 7th Street intersection is back open to two lanes and all the concrete pavement is complete in the intersection. All the concrete in the 5th Street intersection was also completed last weekend during the LRT shutdown.
Work has begun in the 6th St intersection.
What's Coming Up
Continued concrete paving work be taking place in the 6th Street intersection. This intersection will be reduced to one lane of traffic starting June 20.
The majority of the concrete planters have been completed this week as well as bike lanes.
The 5th Street intersection will re-open for next week.
See update for additional information Hennepin_Update_Vol95.pdf