4th Street Reconstruction Project Update - June 3
4th Street Reconstruction Project Overview
The City of Minneapolis is reconstructing 4th St. between 2nd Ave. N and 4th Ave. S in downtown Minneapolis. The reconstruction will include wider sidewalks, improved crossings, a new bi-directional off-street bike path on the north side of the street, lighting, trees, and planting beds. Construction is underway and is expected to be complete by the end of 2022.
What's Happening Next Week?
Roadway reconstruction continues on 4th St. between 2nd Ave. N and Hennepin Ave. Fourth St. is currently closed to vehicle traffic between 1st Ave. N and Hennepin Ave. Local access is being maintained between 2nd Ave. N and 1st Ave. N.
- Concrete, curb and gutter, and concrete pavement construction will occur on the south side of the roadway between 2nd Ave. N and 1st Ave. N.
- Starting next week, crews will begin sidewalk construction work along the south side of the roadway between 1st Ave. and Hennepin Ave. Pedestrian access will be maintained.
- Lane restrictions at the 1st Ave. intersection continues for roadway paving work.
- Crews will be conducting minor concrete repairs between Hennepin Ave. and 4th Ave. S.
*Please note that the construction schedules are subject to change due to weather and other unforeseen circumstances.
What to expect during construction?
- During roadway construction, 4th St. will be closed to through traffic between 2nd Ave. N and Hennepin Ave. Local access will be maintained from 2nd Ave. N and 1st Ave. N.
- Pedestrian access will be maintained throughout construction. Be aware of your surroundings when walking on the sidewalk and biking in the roadway.
- Expect additional noise, dust, and vibration as crews complete work.
Upcoming Events
4th Street Weekly Stakeholder Meeting
Weekly project newsletters are sent out weekly and virtual stakeholder meetings occur bi-weekly. Join us at the next stakeholder meeting to get project updates, talk with project staff and get your questions/concerns answered.
Upcoming Stakeholder Meetings:
June 17, 9-9:30 a.m.
July 8, 9-9:30 a.m.
Teams Meeting: Click here to join the meeting
Stay connected
There are multiple ways to get information including email updates and ongoing stakeholder meetings. Visit the project website for more information and to sign up for project updates: www.minneapolismn.gov/government/projects/fourth-st-n-and-s/
Provide questions, comments or concerns on the interactive map: https://zan.mysocialpinpoint.com/4thstreetreconstruction
Email the project team: info@4thstmpls.com
Contact the project hotline: 612-412-9774
Pizza Luce alleyway completed and reopened.
Grading for bike trail 1st Avenue N to Hennepin Avenue.