10th Avenue Bridge and Water Main Project Update - August 24, 2020
The 10th Avenue Bridge will be closed and detours will be in effect for approximately 18 months, until Summer 2021. This project will rehabilitate the historic 10th Ave SE bridge over the Mississippi River and W River Pkwy. A new water main will be installed under the river as part of the project. More info.
Latest Projct News
Construction Update Meeting - Friday, August 28, 2020 - at 10:30 a.m.
Project staff will hold a virtual construction update meeting this Friday using GoTo Meeting. Members of the public are invited to join the online meeting and hear updates on construction progress and speak with project staff.
Please use this link to join the 10th Ave Bridge Online Construction Update Meeting from your computer, tablet or smartphone:
https://global.gotomeeting.com/join/784924461
You can also dial in using your phone.
United States: +1 (224) 501-3412
Access Code: 784-924-461
The bridge was closed on March 30th and the contractor has been actively working on repairs. For more details on the repairs, schedule and bridge deck changes, please see the latest Construction Update or go to the project page 10th Ave Bridge.
What's Coming Up
The bridge will remain closed to all traffic including, vehicles, bikes, and pedestrians until Summer 2021.
West River Parkway (roadway only) will be closed to motor vehicles through November 1, 2020. The adjacent trail will remain open for bicyclists and pedestrians.
Work requires the use of heavy equipment that will increase noise, vibration, and dust in work areas.
Access to adjacent apartments and businesses will remain open during the construction activity.
Project Contacts:
Bridge Contact: Meseret Wolana, meseret.wolana@minneapolismn.gov or 612-673-3527
Water Main Contact: Peter Pfister, peter.pfister@minneapolismn.gov or 612-661-4906