The North Loop Reconstruction & Pedestrian Improvements Project consists of two separate projects:
- A full street reconstruction along 3rd St N between 10th Ave N and 5th Ave N
- A pedestrian improvement project generally bounded by 10th Ave N on the north, 1st Ave on the south, West River Parkway on the east, and 4th St N on the west
North Loop Reconstruction Updates
WORK THIS PAST WEEK
5th Ave N
- Began driveway placement
- Began installing curb and gutter
- Began installing light bases
- Continued installing conduit for lights
- Placed the second lift of asphalt from 4th St N to Washington
7th Ave N
- Continue work on the north side of Washington
8th Ave N
- Grading for walks and driveways
- Continued sidewalk placement
- Continued placing driveways
- Continued work on the north side of Washington
- Started placing parking bays
9th Ave N
- Continued placing driveways
- Continued placing sidewalks
- Continued work on the north side of Washington
3rd St N
- Finished amending poor soils between 8th and 10th Aves N
- Finished grading and bringing in aggregate in preparation for paving
- Placed the first lift of asphalt from 5th Ave N to 6th Ave N
- Continuing the underground utility work
- Began relocating power poles
WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK
5th Ave N
- Continue with driveway placement
- East side sidewalk placement
- Continue with light foundation installation
- Remove globe lights on the east side of 5th Ave N
7th Ave N
- Place the 3rd lift of asphalt either 7-30 or 8-4
- Finish placing driveways
- Continue work on the north side of Washington
8th Ave N
- Finish placing sidewalks
- Finish placing driveways
- Continue work on the north side of Washington
9th Ave N
- Continue placing driveways
- Continue placing sidewalks
- Continue work on the north side of Washington
3rd St N
- Complete underground utility work
- Placement of the first lift of asphalt is tentatively planned between 8-30 and 9-4
- 6th Ave N to 7th Ave N Currently paving this
- 7th Ave N to 10th Ave N -Hoping to finish this stretch today 8-30, if not will continue next week
- Installation of curb and gutter will follow asphalt placement
For more information on this project, visit the project website.
North Loop Pedestrian Improvements Updates
Crews will be coming back in September to finish up the job.
WORK THIS PAST WEEK
- 1st St N & 4th Ave –Finished water work
- 2nd St N and 3rd Ave N – Continuing sewer work
REMAINING WORK ON THIS PROJECT
1st St N
- 2nd Ave SE corner
- 4th Ave SE and NE corner
2nd St N
- 1st Ave N - All corners
- 2nd Ave N – NE, SE and SW
- 3rd Ave N – All, currently the City is working in this intersection, pedestrian ramps will be done after the sewer work is complete
- 5th Ave N – SE corner
- 8th Ave N – South side and NE corner
- 10th Ave N – SE and SW corners
4th St N
- 10th Ave N – NE corner
- 7th Ave N – South side
Other
- All signal installation will start late in September due to long lead times on materials
- Remaining concrete work will continue through September
For more information on this project, visit the project website.
Miscellanious
Stakeholder Meeting -These meetings are informal, held biweekly and intended to offer residents and businesses on the job an opportunity to get construction updates, ask construction and access related questions.
Contact Information
Project Manager: Stephanie Malmberg, stephanie.malmberg@minneapolismn.gov, 612-673-3365
Chief Field Inspector: John Benjamin, john.benjamin@minneapolismn.gov, 651-443-1096