North Loop Reconstruction & Pedestrian Improvements
Editor's note - This is an ongoing series of updates as the North Loop Reconstruction and Pedestrian Improvements project.
North Loop Reconstruction & Pedestrian Improvements
The North Loop Reconstruction & Pedestrian Improvements Project consists of two separate projects:
- A full street reconstruction along 3rd St N between 10th Ave N and 5th Ave N
- A pedestrian improvement project generally bounded by 10th Ave N on the north, 1st Ave on the south, West River Parkway on the east, and 4th St N on the west
North Loop Reconstruction Updates
WORK THIS PAST WEEK
5th Ave N
- All underground utility work completed
- All soil corrections completed
- Started placing gravel in preparation for paving
7th Ave N
- Began curb and gutter placement
- Began driveway placement
- Light foundations and conduit installed
8th Ave N
- Curb and Gutter placed at the Washington end
- Started preparations to reinstall salvaged granite curb
9th Ave N
- Curb and gutter placed at Washington and partially along the west side of 9th Ave N
3rd St N
- Finished salvaging brick pavers and granite curb
- Completed pavement removals, with the exception of the south sidewalk
- Finished water work
- Started sanitary and storm work
WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK
5th Ave N
- Placement of the first lift of asphalt tentatively scheduled for Wednesday August 14,local access to 5th Ave N between Washington Ave and 5th St N will be open; however, plan for delays entering and leaving the area
- Curb and gutter installation will follow asphalt placement
- Driveway installation is scheduled to begin the week of August 19
7th Ave N
- Finish placement of driveways, once the driveway has reached the required strength to carry traffic a gravel ramp will be placed at the roadway end of the driveway apron
- Start placement of sidewalks
- Placement of the second lift of asphalt tentatively scheduled for August 15th – 16th
8th Ave N
- Install granite curb
- Placement of the second lift of asphalt at Washington tentatively scheduled for August 14th – 16th
- Once the second lift of asphalt is placed local access from and to Washington Ave will be allowed
- Concrete crews may begin the installation of concrete parking bays
9th Ave N
- Placement of the second lift of asphalt at Washington tentatively scheduled for August 15th – 16th
- Once the second lift of asphalt is placed local access from and to Washington Ave will be allowed
3rd St N
- Complete underground utility work
- Begin amending poor soils
- Begin grading and bringing in aggregate in preparation for paving
For more information on this project, visit the project website.
North Loop Pedestrian Improvements Updates
The concrete crews are off site until the end of the month, however the sewer and water crews will be doing intermittent work in the next few weeks.
REMAINING WORK ON THIS PROJECT
1st St N
- 2nd Ave SE corner
- 4th Ave SE and NE corner
2nd St N
- 1st Ave N - All corners
- 2nd Ave N – NE, SE and SW
- 3rd Ave N – All, currently the City is working in this intersection, pedestrian ramps will be done after the sewer work is complete
- 5th Ave N – SE corner
- 8th Ave N – South side and NE corner
- 10th Ave N – SE and SW corners
4th St N
- 10th Ave N – NE corner
- 7th Ave N – South side
Other
- All signal installation will start late in September due to long lead times on materials
- Remaining concrete work will continue through September
For more information on this project, visit the project website.
Miscellanious
Stakeholder Meeting -These meetings are informal, held biweekly and intended to offer residents and businesses on the job an opportunity to get construction updates, ask construction and access related questions.
Contact Information
Project Manager:
Stephanie Malmberg, stephanie.malmberg@minneapolismn.gov, 612-673-3365
Chief Field Inspector:
John Benjamin, john.benjamin@minneapolismn.gov, 651-443-1096