North Loop Reconstruction & Pedestrian Improvements
Editor's note - This is an ongoing series of updates as the North Loop Reconstruction and Pedestrian Improvements project.
North Loop Reconstruction & Pedestrian Improvements
The North Loop Reconstruction & Pedestrian Improvements Project consists of two separate projects:
- A full street reconstruction along 3rd St N between 10th Ave N and 5th Ave N
- A pedestrian improvement project generally bounded by 10th Ave N on the north, 1st Ave on the south, West River Parkway on the east, and 4th St N on the west
North Loop Reconstruction Updates
WORK THIS PAST WEEK
5th Ave N
- Continuing water work at 5th and 3rd St N
- Continue soil corrections between 3rd St and 4th St N
- Began storm sewer work
7th Ave N
- Placed 1st lift of asphalt
8th Ave N
- Placed the 1st lift of asphalt (at Washington Ave only)
9th Ave N
- Placed the 1st lift of asphalt (at Washington Ave and the west side of 9th Ave N)
3rd St N
- Continued water work between 8th Ave N and 5th Ave N
- Finished salvaging brick pavers on the north side of 3rd St N between 10th Ave N and 7th Ave N, and started the south side removals
- Removal of north sidewalk & curb between 10th & 5th Avenue
- Frana began work on the Bassett Creek Apartments, currently connecting storm, sanitary, water and a new hydrant into 3rd St N (this is why 3rd St N has been closed off at 7th Ave N)-the utility connections work should be complete by early next week.
WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK
5th Ave N
- Continuing water work at 5th and 3rd St N (8th Ave N to 5th Ave N)
- Hydrant installation at 4th Ave N
- Complete sanitary sewer work
- Complete storm sewer work
- Begin grading and hauling in gravel in preparation for paving
7th Ave N
- Begin concrete installation (curb and gutter placement and possibly driveway placement) starting Monday 7-29
- Access to properties between Washington and 3rd St N will partially reopen at Washington soon as 3rd St N removals have begun
8th Ave N
- Begin concrete installation (curb and gutter placement and possibly driveway placement) starting Monday 7-29
- Access to properties between Washington and 3rd St N will partially reopen at Washington soon as 3rd St N removals have begun
9th Ave N
- Begin concrete installation (curb and gutter placement and possibly driveway placement) starting Monday 7-29
- Access to properties between Washington and 3rd St N will partially reopen at Washington soon as 3rd St N removals have begun
3rd St N
- Possible water work on 3rd St between 7th Ave N and 8th Ave N
- Pedestrian access will be maintained on the south side of 3rd St N
- Milling asphalt between 5th and 6th Aves N
- Bassett Creek Apartment excavation to commence soon
For more information on this project, visit the project website.
North Loop Pedestrian Improvements Updates
WORK THIS PAST WEEK
1st St N
- 3rd Ave N-water work completed
- 4th Ave N- placed concrete on SW corner
- 2nd Ave N -SW corner removed, storm sewer work in process
- 2nd Ave N-NE and NW intersections removed
- 8th Ave N Pour remaining concrete along 1st Ave N
2nd St N North Side
- 4th Ave N – Poured remaining concrete
- 5th Ave N –Poured remaining concrete
- 8th Ave N - Electrical work for Pedestrian Crosswalk system and poured remaining concrete
- 10th Ave N-North side poured except a few panels
4th Ave and W River Parkway
- North side of Parkway complete
10th Ave N
- 4th St N – remove pavement on north side
- 4th St N – Removed trees
WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK
1st St N
- 1st Ave N – Asphalt paving
- 2nd Ave N – Finish removals on the north side and begin pouring new ped ramps, curb and sidewalk, asphalt paving
- 3rd Ave N- Asphalt paving SE corner, remove SW corner, remove north side
- 8th Ave N – Complete concrete paving
- 3rd Ave N-Remove SW corner and North side
2nd St N
- 3rd Ave N – Storm sewer work will begin August 5 on east side. This is a separate project, once it is complete the pedestrian ramps will be constructed
- 4th Ave N pour remaining concrete
- 5th Ave N pour remaining concrete
- 8th Ave N begin installing conduit for new pedestrian flasher system. Pour remaining concrete
10th Ave
- 4th St N – Relocate hydrant
- 4th St N- Pour concrete
For more information on this project, visit the project website.
Miscellanious
Stakeholder Meeting -These meetings are informal, held biweekly and intended to offer residents and businesses on the job an opportunity to get construction updates, ask construction and access related questions.
Date/Time: August 7, 7:30 am to 8:30 am
Location: Corner Coffee 514 N 3rd St #102
Contact Information
Project Manager:
Stephanie Malmberg, stephanie.malmberg@minneapolismn.gov, 612-673-3365
Chief Field Inspector:
John Benjamin, john.benjamin@minneapolismn.gov, 651-443-1096