10th Ave Bridge and Watermain Project
This project will rehabilitate the historic 10th Ave SE bridge over the Mississippi River and W River Pkwy. A new water main will be installed under the river as part of the project.
Latest Project News
Construction Update Meeting - Friday, March 19, 2021 at 10:30 am
Project staff will hold a virtual construction update meeting next Friday using GoTo Meeting. Members of the public are invited to join the online meeting and hear updates on construction progress and speak with project staff.
Please use this link to join the 10th Ave Bridge Online Construction Update Meeting from your computer, tablet or smartphone: https://global.gotomeeting.com/join/784924461
You can also dial in using your phone: 1 (224) 501-3412, Access Code: 784-924-461
The bridge was closed on March 30th, 2020 and the contractor has been actively working on repairs. For more details on the repairs, schedule and bridge deck changes, please see the latest Construction Update or go to the project page 10thavebridge.com.
What's Coming Up
The 10th Ave Bridge will remain closed to all traffic including, vehicles, bikes, and pedestrians until fall 2021.
West River Parkway (roadway only) will be closed to motor vehicles through April 2021. The adjacent trail will remain open for bicyclists and pedestrians.
Work requires the use of heavy equipment that will increase noise, vibration, and dust in work areas.
Access to adjacent apartments and businesses will remain open during the construction activity.
For more information on this project contact:
Bridge Contact: Meseret Wolana, meseret.wolana@minneapolismn.gov or 612-673-3527