Kim Eslinger
Editor
612-321-8040
kim@millcitymedia.org

Brianna Ojard
Associate Editor

David Tinjum
Publisher
612-321-8020
dave@millcitymedia.org

Claudia Kittock
Columnist / Non-Profits
Email Claudia...

Becky Fillinger
Small Business Reporter
Producer / Milling About
Email Becky...

Michael Rainville Jr.
History Columnist
Email Michael...

Doug Verdier
River Matters

Mill City Times is a not-for-profit community service. We do not sell advertising on this site.

Community Partners

Thanks to our community partners, whose support makes Mill City Times possible:

MILL CITY FARMERS MARKET

With over 100 local farmers, food makers and artists, MCFM strives to build a local, sustainable and organic food economy in a vibrant, educational marketplace.

Visit their website...

HENNEPIN HISTORY MUSEUM

Hennepin History Museum is your history, your museum. We preserve and share the diverse stories of Hennepin County, MN. Come visit!

Visit their website...

MEET MINNEAPOLIS

Maximizing the visitor experience of Minneapolis for the economic benefit of our community, making Minneapolis the destination of choice among travelers.

Visit their website...

MSP FILM SOCIETY

Promoting the art of film as a medium that fosters cross-cultural understanding, education, entertainment, and exploration.

Visit their website...

GREAT RIVER COALITION

Enhancing the Minneapolis riverfront environment—for people and pollinators.

Visit their website...

Cultural Cornerstones
Search Mill City
Recent News
Front Page Archives
Friday
May312024

May 2024 Minneapolis Central City Tunnel Project Update

Via a May 31 e-announcement from the City of Minneapolis:

Project Overview

The City of Minneapolis Public Works Department is constructing a new parallel storm tunnel, enlarging a portion of the existing storm tunnel, and constructing a new tunnel access in Downtown Minneapolis.

The new tunnel is being constructed parallel to the existing tunnel located under Washington Ave S between Nicollet Mall and Chicago Ave. The existing tunnel under Chicago Ave between Washington Ave S and the Mississippi River is being expanded to handle the increased stormwater capacity. The purpose of this project is to reduce pressure in the existing tunnel, provide more room for future growth, and to reduce the need for future repairs and tunnel failures.

Project News

Crews continue to work on the new parallel storm tunnel. The mining process is complete and the last concrete pours are scheduled for the coming weeks. Restoration of the storm tunnel outlet at the Mississippi River has begun and barring any unforeseen circumstances, the access portals at 2nd Avenue and Portland Avenue will be cleaned up by mid-June.

Mississippi River Portal

  • Crews continue reconstructing the storm tunnel outlet at the Mississippi River.

2nd Ave

  • Crews are wrapping up work on the concrete liner for the new storm tunnel under Washington Avenue.

Portland Ave

  • Crews are wrapping up work on the concrete liner for the new storm tunnel under Washington Avenue.

Dewatering Well Sites

  • Crews will be working on the removal of the dewatering wells. Partial closures of sidewalks and streets will occur during the work.

Project Map

Stay Connected

Visit the project website for more information and to sign up for project updates: https://www.minneapolismn.gov/government/projects/central-city-tunnel/

Email the project team: info@mplscentralcitytunnel.com

Contact the project hotline: 612-888-9418

« Kolman & Reeb Gallery's Project Space Grant presents Foreign Bodies by Kate Casanova June 15-Aug 3 | Main | Minneapolis DID and IKE Smart City Launch Digital Wayfinding Kiosks »